Work Profile Report [47W379]

जनपद टिहरी गढ़वाल के विकास खण्ड़ कीर्तिनगर के अन्तर्गत जैधार बैण्ड से माछनी मोटर मार्ग का नवनिर्माण।

    Tenders

    Aggrements

    Project Activities

    alerts

    Samples

Administrative Approval Detail : शा0सं0 2277/।।।(2)/19-10(एम0एल0ए0)/2017 टी0सी0 दिनांक 21.06.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

13.53

Resanction Cost :

13.53

Tentative Cost :

13.53

Exp. Upto Last Fy :

4.22

For CFY 2025-2026

Remaining :

9.31

Demand :

7.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

4.22

Alignment Approved

Sanction on : 5 years 9 months ago

21 Jun 2019

Physical Progress:

At start of FY 2025-2026 :

40 %

Up to Date :

40 %

Tentative Completion date on : 11 months 2 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
3.000
0.000

Remark

view all

प्रकरण विधिवत स्वीकृति हेतु प्रभागीय वनाधिकारी स्तर पर लम्बित है। -- as on 24-Dec-2024

Rating : 56

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval

Loading...