Work Profile Report [47W441]

क्वीली से मछियारी होते हुये नैखरी तक मोटर मार्ग का नवनिर्माण (द्वितीय चरण, पार्ट-।)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents

Administrative Approval Detail : 1338/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी-।।।. दि0 11.05.2021

TS Amount (lakhs) : 130.99 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

130.99

Resanction Cost :

130.99

Tentative Cost :

130.99

Exp. Upto Last Fy :

126.21

For CFY 2024-2025

Remaining :

4.78

Demand :

4.78

Allotment :

2.00

Exp in CFY :

0.00

Total Up to Date Exp :

126.21

Construction Started

Sanction on : 3 years 3 months ago

11 May 2021

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

90 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.500
0.000

Remark

view all

4.5 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर है । -- as on 14-Jul-2024

Rating : 141

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: