Work Profile Report [47W456]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 3258/III(2)/21-10(MLA)/2017 TC Dt. 02.09.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.88
Resanction Cost :
51.88
Tentative Cost :
51.88
Exp. Upto Last Fy :
1.93
For CFY 2025-2026
Remaining :
49.95
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.93
Alignment Approved
Sanction on : 4 years 4 months ago
02 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 2 months 4 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज-1 की डी0पी0आर0 शासन से आपत्तियों में प्राप्त। आपत्तियों का ंनिराकरण किया जा रहा है। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: