Administrative Approval Detail : 4987(1)/III(2)/21-10(MLA)/2017 TC Dt. 22.10.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.35
Resanction Cost :
53.35
Tentative Cost :
53.35
Exp. Upto Last Fy :
24.48
For CFY 2025-2026
Remaining :
28.87
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
24.48
Alignment Approved
Sanction on : 3 years 5 months ago
22 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
60 %
Tentative Completion date on : 11 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर वितरण की कार्यवाही गतिमान है। -- as on 22-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: