Work Profile Report [47W462]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 4954(1)/III(2)/21-10(MLA)/2017 TC-III Dt. 14.10.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.94
Resanction Cost :
56.94
Tentative Cost :
56.94
Exp. Upto Last Fy :
0.94
For CFY 2025-2026
Remaining :
56.00
Demand :
2.00
Allotment :
4.89
Exp in CFY :
0.74
Total Up to Date Exp :
1.68
Alignment Approved
Sanction on : 4 years 2 months ago
14 Oct 2021
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग वनभूमि से आच्छादित हैए जो कि आॅनलाइन किया जा चुका है। सैद्धान्तिक स्वीकृति के पश्चात ही अग्रिम कार्यवाही की जायेगी। -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand