Work Profile Report [47W465]

टकोली से रणसोली होते हुये त्यालनी मोटर मार्ग का नव निर्माण कार्य (प्रथम चरण)। (24 मीटर स्पान सेतु सहित)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 5695/III(2)/21-10(MLA)/2017 Dt. 24.11.2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

40.10

Resanction Cost :

40.10

Tentative Cost :

40.10

Exp. Upto Last Fy :

0.07

For CFY 2025-2026

Remaining :

40.03

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.07

Alignment Approved

Sanction on : 3 years 4 months ago

24 Nov 2021

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

20 %

Tentative Completion date on : 11 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4.775
0.000
4.775
4.775
0.000
Bridge
1 (24m)
1 (24m)
0 (0.000m)
1 (24m)
1 (24.000m)
0 (0.000m)

Remark

view all

वनभूमि हस्तान्तरण प्रस्ताव गठित किया जा रहा है। -- as on 24-Dec-2024

Rating : 33

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: