Work Profile Report [47W533]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं0 -470/।।।(2)/22-10(एम0एल0ए0)/2017 टी0सी0-। दिनांक 07.01.2022
TS Amount (lakhs) : 498.41 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
498.41
Resanction Cost :
498.41
Tentative Cost :
498.41
Exp. Upto Last Fy :
437.71
For CFY 2024-2025
Remaining :
60.70
Demand :
60.70
Allotment :
41.50
Exp in CFY :
31.70
Total Up to Date Exp :
469.41
Construction Started
Sanction on : 2 years 7 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 day ago
15 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 15-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: