Administrative Approval Detail : शासन की ई-फाईल सं0-49188 दिनंाक 28.03.2023
TS Amount (lakhs) : 166.87 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
166.87
Resanction Cost :
166.87
Tentative Cost :
166.87
Exp. Upto Last Fy :
92.26
For CFY 2025-2026
Remaining :
74.61
Demand :
74.61
Allotment :
74.60
Exp in CFY :
10.90
Total Up to Date Exp :
103.16
Construction Started
Sanction on : 2 years 5 months ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
62 %
Up to Date :
90 %
Tentative Completion date on : 2 weeks 12 hours ago
15 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.500 किमी0 में पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 18-Aug-2025
Assets :
Work not linked with IM