Work Profile Report [47W546]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल सं0-36456 दिनंाक 09.11.2022
TS Amount (lakhs) : 52.57 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
52.57
Resanction Cost :
52.57
Tentative Cost :
52.57
Exp. Upto Last Fy :
3.81
For CFY 2024-2025
Remaining :
48.76
Demand :
48.76
Allotment :
23.00
Exp in CFY :
21.89
Total Up to Date Exp :
25.69
Work deferred
Sanction on : 2 years 1 month ago
09 Nov 2022
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
यू0पी0सी0एल द्वारा बिजली के पोल शिफ्ट करने के पश्चात ही कार्य प्रारम्भ किया जायेगां। -- as on 24-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: