Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.68 | 14.68 | 0.000 | 14.68 | 14.680 | 0.000 |
47W555 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 895/07 Yata-PMGSY-ni.-III Dt. 16.05.2023
TS Amount (lakhs) : 253.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
253.07
Resanction Cost :
253.07
Tentative Cost :
253.07
Exp. Upto Last Fy : 89.96
For CFY 2024-2025
Remaining : 163.11
Demand : 163.11
Allotment : 117.25
Exp in CFY : 117.23
Total Up to Date Exp : 207.19
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्च शेष। -- as on 26-Jun-2024
Physical Peramenters