Work Profile Report [47W556]

विकासखण्ड़ कीर्तिनगर के अन्तर्गत कोठार लिंक मोटर मार्ग के कि0मी0 1 (हे0मी0 0-2 एवं 8-10 पर अतिरिक्त पहाड़ कटान एवं अवशेष कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : DM-Tehri Ltr No-161/-Jio-2017-18 Date 09.05.2018

TS Amount (lakhs) : 35.9 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

35.90

Resanction Cost :

35.90

Tentative Cost :

35.90

Exp. Upto Last Fy :

23.48

For CFY 2024-2025

Remaining :

12.42

Demand :

10.00

Allotment :

0.00

Exp in CFY :

4.93

Total Up to Date Exp :

28.41

Work completed

Sanction on : 6 years 6 months ago

09 May 2018

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
0
0

Remark

view all

कार्य पूर्ण दायित्व शेष। -- as on 24-Jul-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand