Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.5 | 5.5 | 0.000 | 5.5 | 5.500 | 0.000 |
47W574 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 92.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.22
Resanction Cost :
92.22
Tentative Cost :
92.22
Exp. Upto Last Fy : 19.95
For CFY 2024-2025
Remaining : 72.27
Demand : 72.27
Allotment : 10.00
Exp in CFY : 4.15
Total Up to Date Exp : 24.10
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
3 weeks 1 day ago
25 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 27-Jun-2024