Work Profile Report [47W581]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-49188 Dt- 25-09-2023
TS Amount (lakhs) : 171.47 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
171.47
Resanction Cost :
171.47
Tentative Cost :
171.47
Exp. Upto Last Fy :
0.29
For CFY 2024-2025
Remaining :
171.18
Demand :
50.00
Allotment :
61.70
Exp in CFY :
76.53
Total Up to Date Exp :
76.82
Construction Started
Sanction on : 1 year 1 month ago
25 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.50 कि0मी0 लम्बाई में पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: