Work Profile Report [47W583]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-49188 Dt- 25-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
4.39
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.11
Alignment Approved
Sanction on : 1 year 1 month ago
25 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 09/2023 में स्वीकृत हुआ है। कार्य के प्रथम चरण की कार्यवाही गतिमान है। -- as on 15-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand