Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 23 | 23 | 23 | 0 |
47W588 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 5082/07/(2)/2023-01(प्रा0आ0) Dt. 09.11.2023
TS Amount (lakhs) : 165.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
165.57
Resanction Cost :
165.57
Tentative Cost :
165.57
Exp. Upto Last Fy : 153.68
For CFY 2024-2025
Remaining : 11.89
Demand : 11.89
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 153.68
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर सुरक्षात्मक दृष्टि से पैरापिट व क्रश बैरियर का निर्माण किया जा रहा है। -- as on 21-Mar-2024
Physical Peramenters