Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
47W591 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-39499 Dt- 02-08-2023
TS Amount (lakhs) : 181.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
181.26
Resanction Cost :
181.26
Tentative Cost :
181.26
Exp. Upto Last Fy : 0.76
For CFY 2024-2025
Remaining : 180.50
Demand : 50.00
Allotment : 3.00
Exp in CFY : 2.73
Total Up to Date Exp : 3.49
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
11 months 2 weeks ago
02 Aug 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे सीमांकन की धनराशि वन विभाग के पक्ष में जमा करने की कार्यवाही गतिमान है। -- as on 14-Jul-2024
Physical Peramenters