Work Profile Report [47W604]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-39499/10 Dt- 07-02-2024
TS Amount (lakhs) : 180.05 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
180.05
Resanction Cost :
180.05
Tentative Cost :
180.05
Exp. Upto Last Fy :
52.56
For CFY 2024-2025
Remaining :
127.49
Demand :
50.00
Allotment :
120.00
Exp in CFY :
61.85
Total Up to Date Exp :
114.42
Construction Started
Sanction on : 9 months 2 weeks ago
07 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
65 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.50 कि0मी0 में पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर है। -- as on 26-Jul-2024