Work Profile Report [47W611]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-39205 Dt- 12-03-2024
TS Amount (lakhs) : 175.74 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
175.74
Resanction Cost :
175.74
Tentative Cost :
175.74
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
175.64
Demand :
140.00
Allotment :
140.00
Exp in CFY :
134.22
Total Up to Date Exp :
134.32
Construction Started
Sanction on : 9 months 1 week ago
12 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
92 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.60 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: