Work Profile Report [47W635]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E. File No 39205 Dated 29-10-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.80
Resanction Cost :
81.80
Tentative Cost :
81.80
Exp. Upto Last Fy :
39.02
For CFY 2025-2026
Remaining :
42.78
Demand :
42.78
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
39.02
Construction Started
Sanction on : 5 months 1 week ago
29 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
70 %
Tentative Completion date on : 2 months 3 weeks from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 किमी0 में पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 25-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: