Work Profile Report [49W109]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0स0 5060/।।।(2)/13-21(प्रा0आ0)/13 दि0 12/09/2013
TS Amount (lakhs) : 184.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
184.50
Resanction Cost :
184.50
Tentative Cost :
184.50
Exp. Upto Last Fy :
125.87
For CFY 2025-2026
Remaining :
58.63
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
125.87
Phase1 DPR Submitted
Sanction on : 12 years 3 months ago
12 Sep 2013
Physical Progress:
At start of FY 2025-2026 :
68 %
Up to Date :
68 %
Tentative Completion date on : 2 years 2 months from now
31 Mar 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कुछ ग्रामीणों द्वारा प्रतिकर नहीं लिया जा रहा है जिस कारण प्रतिकर भुगतान हेतु दायित्व अवशेष | द्वितीय चरण का कार्य पूर्ण | -- as on 08-Oct-2025
Assets :
Work not linked with IM