Work Profile Report [49W210]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0-1869/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-07.06.2016
TS Amount (lakhs) : 102.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
102.20
Resanction Cost :
102.20
Tentative Cost :
102.20
Exp. Upto Last Fy :
77.39
For CFY 2024-2025
Remaining :
24.81
Demand :
1.16
Allotment :
9.69
Exp in CFY :
12.68
Total Up to Date Exp :
90.07
Alignment Approved
Sanction on : 8 years 5 months ago
07 Jun 2016
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण | -- as on 06-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: