Work Profile Report [49W222]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0- 2198/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-25.07.2016
TS Amount (lakhs) : 47.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.20
Resanction Cost :
47.20
Tentative Cost :
47.20
Exp. Upto Last Fy :
1.91
For CFY 2025-2026
Remaining :
45.29
Demand :
44.29
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.91
Alignment Approved
Sanction on : 9 years 3 months ago
25 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 months 3 days ago
31 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पूर्व में स्वीकृत सरेखन हेतु ग्रामीणों की सहमती न होने के फलस्वरूप पुनः सर्वेक्षण की कार्यवाही गतिमान | -- as on 17-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: