Work Profile Report [49W319]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : अपर सचिव/परियोेजना समन्यव्यक ग्राम्य विकास सचिवालय परिसर के शा0 सं0-171/टी0सी0-(1)/65/एस0पी0एू0यू0/आर0डी0/2016/ दि0 27.01.2018
TS Amount (lakhs) : 405 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
405.00
Resanction Cost :
405.00
Tentative Cost :
405.00
Exp. Upto Last Fy :
203.49
For CFY 2025-2026
Remaining :
201.51
Demand :
20.20
Allotment :
20.20
Exp in CFY :
20.20
Total Up to Date Exp :
223.69
Construction Started
Sanction on : 7 years 10 months ago
27 Jan 2018
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पार्किंग फिनिशिंग का कार्य प्रगति पर | -- as on 05-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: