Work Profile Report [49W331]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन का पत्र सं0-2162/।।।(2)/19-25(प्राआ0)/2017 दिनाॅक 10.06.2019
TS Amount (lakhs) : 409.84 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
409.84
Resanction Cost :
409.84
Tentative Cost :
409.84
Exp. Upto Last Fy :
405.04
For CFY 2024-2025
Remaining :
4.80
Demand :
0.86
Allotment :
0.63
Exp in CFY :
0.86
Total Up to Date Exp :
405.90
Work completed
Sanction on : 5 years 2 months ago
10 Jun 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 2 months ago
13 Jun 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्वों का भुगतान शेष। कार्य की वास्तविक समाप्ति की तिथि 13-06-2021 है। -- as on 06-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: