Work Profile Report [49W332]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 3269/।।।(2)/ 19-03 (मु0मं0घो0) /201ं दि0 03.09.2019
TS Amount (lakhs) : 325.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
325.50
Resanction Cost :
325.50
Tentative Cost :
325.50
Exp. Upto Last Fy :
297.18
For CFY 2024-2025
Remaining :
28.32
Demand :
28.32
Allotment :
4.17
Exp in CFY :
4.17
Total Up to Date Exp :
301.34
Work completed
Sanction on : 5 years 3 months ago
03 Sep 2019
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 2 months 2 days from now
28 Feb 2025
Actual Completion Date : 3 months 2 weeks ago
05 Sep 2024
Physical Linear Components
Remark
कार्य पूर्ण,दायित्व शेष | -- as on 05-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand