Work Profile Report [49W469]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0- 461/।।।(2)/22-01(मा0मु0 घो0)/2018टी0सी0 दिनाॅक-07.01.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.83
Resanction Cost :
58.83
Tentative Cost :
58.83
Exp. Upto Last Fy :
46.34
For CFY 2024-2025
Remaining :
12.49
Demand :
10.00
Allotment :
12.00
Exp in CFY :
9.22
Total Up to Date Exp :
55.57
Work completed
Sanction on : 2 years 10 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date : 1 year 2 months ago
31 Aug 2023
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: