Work Profile Report [49W524]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई पत्रावली संख्या- 49198 /दिनांक 18.05.2023
TS Amount (lakhs) : 3.72 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.72
Resanction Cost :
3.72
Tentative Cost :
3.72
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
3.62
Demand :
3.00
Allotment :
1.37
Exp in CFY :
1.37
Total Up to Date Exp :
1.47
Survey work done
Sanction on : 1 year 7 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
5 %
Tentative Completion date on : 3 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डीपीआर नई दरो पर गठित कर दिनांक 15.01.2025 तक प्रेषित कर दी जाएगी | -- as on 25-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand