Work Profile Report [49W658]

Improvement of Pujarganw Inter College road from Light Vehicle Road (LVR) to Motor Road .
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शासन का ई-पत्रांक:- 75508/11 दिनांक 31 दिसम्बर 2025

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

111.11

Resanction Cost :

111.11

Tentative Cost :

111.11

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

111.11

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

in Tendering Stage

Sanction on : 3 weeks 2 days ago

31 Dec 2025

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

0 %

Tentative Completion date on : 2 years 4 months from now

31 May 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
0.75
0.75
0.75
-

Remark

view all

कार्य हेतु दिनांक 06-01-2026 को E टेंडरिंग के माध्यम से आइटम रेट के आधार पर निविदा आमंत्रित की गयी है |निविदा को दिनांक 28-01-2026 को खोला जाना प्रस्तावित है | -- as on 07-Jan-2026

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand