Work Profile Report [49W73]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 5810(1)/।।।(2)10-18(प्रा0आ0)/2010 टी0सी0-।। दिनाॅक-20.09.2010
TS Amount (lakhs) : 25.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy :
7.86
For CFY 2025-2026
Remaining :
17.34
Demand :
0.20
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.86
Survey work done
Sanction on : 14 years 10 months ago
20 Sep 2010
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
35 %
Tentative Completion date on : 7 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों के साथ बैठक कर प्रस्तावित संरेखण पर सहमति नहीं बन पाई, पुनः सहमती बनाने का प्रयास किया जा रहा है -- as on 01-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: