Work Profile Report [49W77]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 5157(1)/।।।(2)10-18(मु0मं0घो0)/2010 दिनाॅक 9.11.2010
TS Amount (lakhs) : 178.08 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
178.08
Resanction Cost :
178.08
Tentative Cost :
178.08
Exp. Upto Last Fy :
168.33
For CFY 2024-2025
Remaining :
9.75
Demand :
5.30
Allotment :
9.75
Exp in CFY :
5.30
Total Up to Date Exp :
173.63
Phase1 DPR Submitted
Sanction on : 14 years 2 weeks ago
09 Nov 2010
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण का कार्य पूर्ण। द्वितीय चरण की स्वीकृति प्राप्त,जिस पर कार्य प्रगति पर है। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: