Work Profile Report : 4W22

महाकालेश्वर-बसभीड़ा मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं. 2555/ 111-2/06 -41(प्रा्र.आ.)/06 दिनांक 26.9.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

178.00

Resanction Cost :

178.00

Tentative Cost :

11.44

Saving

166.56

Exp. Upto Last Fy :

9.44

For CFY 2025-2026

Remaining :

168.56

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

9.44

Alignment Approved

Sanction on : 19 years 4 months ago

26 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 1 year 8 months from now

31 Oct 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
0.000
10
0.000
0.000

Remark

view all

Overall Saving 166.56 has been recorded as expected cost of work reduced from 178 to 11.44 .
पुनः इस कार्यालय के पत्रांक 2324/18सी. दिनांक 02.12.2025 द्वारा जिलाधिकारी, अल्मोड़ा को क्षतिपूरक वृक्षारोपण हेतु प्रेषित। वन भूमि हस्तान्तरण हेतु सी0ए0 लैण्ड उपलब्ध न होने के कारण बचत हुई है।
-- as on 30-Dec-2025

Rating : 5

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : CA Land

Assets :

Work not linked with IM

Bridges on The Basis of AI: