Work Profile Report [4W648]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाईल नं018906 दिनांक14.3.2023
TS Amount (lakhs) : 352.4 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
352.40
Resanction Cost :
352.40
Tentative Cost :
351.40
Saving
1.00
Exp. Upto Last Fy :
178.52
For CFY 2024-2025
Remaining :
173.88
Demand :
173.00
Allotment :
173.00
Exp in CFY :
101.79
Total Up to Date Exp :
280.31
In Maintenance After Completion
Sanction on : 1 year 8 months ago
14 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 19 hours ago
02 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 1 has been recorded as expected cost of work reduced from 352.4 to 351.4 .
1-पहाड़ कटान, पार्ट-2 का कार्य पूर्ण, 4.00 किमी0 में अतिरिक्त चैड़ीकरण का कार्य पूर्ण। 4.00 किमी0 में कल्वर्ट का कार्य पूर्ण तथा 4 किमी. में जी1,जी2 एंव जी3 का कार्य पूर्ण, 4किमी. पी0सी0 का कार्य पूर्ण।
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 24.07.2023 एवं कार्य पूर्ण करने की तिथि 23.10.2024 है। कार्य पूर्ण। दायित्व शेष।
2- अनुरक्षण रू. 8.12 लाख।
3- क्वालिटी कंट्रोल रू. 9.16 लाख।
-- as on 21-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: