Work Profile Report [4W648]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाईल नं018906 दिनांक14.3.2023
TS Amount (lakhs) : 352.4 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
352.40
Resanction Cost :
352.40
Tentative Cost :
351.40
Saving
1.00
Exp. Upto Last Fy :
178.52
For CFY 2024-2025
Remaining :
173.88
Demand :
173.00
Allotment :
173.00
Exp in CFY :
135.38
Total Up to Date Exp :
313.90
In Maintenance After Completion
Sanction on : 1 year 9 months ago
14 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
02 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 1 has been recorded as expected cost of work reduced from 352.4 to 351.4 .
1-पहाड़ कटान, पार्ट-2 का कार्य पूर्ण, 4.00 किमी0 में अतिरिक्त चैड़ीकरण का कार्य पूर्ण। 4.00 किमी0 में कल्वर्ट का कार्य पूर्ण तथा 4 किमी. में जी1,जी2 एंव जी3 का कार्य पूर्ण, 4किमी. पी0सी0 का कार्य पूर्ण।
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 24.07.2023 एवं कार्य पूर्ण करने की तिथि 23.10.2024 है। समयवृद्वि व विचलन के अनुरोध के क्रम अन्तिमीकरण की कार्यवाही गतिमान है।
2- अनुरक्षण रू. 8.12 लाख।
3- क्वालिटी कंट्रोल रू. 9.16 लाख।
-- as on 04-Dec-2024