Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.5 | 0 |
4W66 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं.5150/ (1) /111(2)/10-18(प्रा.आ.)/10 दिनांक 16.8.10
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 44.10 Lacs
Resanction Cost : 44.10 Lacs
Exp. Upto Last Fy : 1.78 Lacs
For CFY 2024-2025
Remaining : 42.32 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.78 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
13 years 8 months ago
16 Aug 2010
Tentative Completion date:
3 years 1 month ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
समरेखन प्रस्ताव अधीक्षण अभियन्ता, अल्मोड़ा के पत्रांक 173/962सी. -01/13 दि. 27.2.13 द्वारा अनुमेदित। अनुमोदित समरेखन में ग्रामवासियों द्वारा विवाद किया जा रहा है। पुनः समरेखन की कार्यवाही की जानी है। ग्रामवासियों द्वारा समरेखन प्रस्ताव परिवर्तन हेतु अनुरोध किया गया है। भूवैज्ञानिक आख्या प्राप्त। संशोधित समरेखन प्रस्ताव इस कार्यालय के पत्र संख्या 3487/1सी. दिनांक 30.12.2023 द्वारा अधीक्षण अभियन्ता, प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा को प्रेषित। समरेखन प्रस्ताव अधीक्षण अभियन्ता, प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा के पत्र संख्या 132/1045सी.-01/2024 दिनांक 23.01.2024 द्वारा आपत्तियों को प्राप्त। आपत्तियों का निराकरण किया जा रहा है। -- as on 21-Feb-2024
Physical Peramenters