Work Profile Report [4W692]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल सं. 60604 दिनांक 07.11.2023
TS Amount (lakhs) : 13.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
13.50
Resanction Cost :
13.50
Tentative Cost :
6.60
Saving
6.90
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
13.40
Demand :
5.00
Allotment :
2.00
Exp in CFY :
1.44
Total Up to Date Exp :
1.54
Alignment Approved
Sanction on : 2 years 2 months ago
07 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
50 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 6.9 has been recorded as expected cost of work reduced from 13.5 to 6.60 . सर्वेक्षण कार्य गतिमान होने के कारण तथा सी0ए0लैण्ड की आवश्यकता होने के कारण बचत हुई है। -- as on 30-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: