Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
51W1083 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : DSCL Letter No 5268/DSCL/20-21
TS Amount (lakhs) : 489.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
479.40
Resanction Cost :
479.40
Tentative Cost :
479.40
Exp. Upto Last Fy : 329.01
For CFY 2024-2025
Remaining : 150.39
Demand : 12.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 329.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
3 years 6 months ago
30 Dec 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में -- as on 21-Oct-2021
Physical Peramenters