Work Profile Report [51W1160]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E Letter No 47588
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
43.56
Resanction Cost :
43.56
Tentative Cost :
43.56
Exp. Upto Last Fy :
34.48
For CFY 2024-2025
Remaining :
9.08
Demand :
9.08
Allotment :
0.60
Exp in CFY :
1.39
Total Up to Date Exp :
35.87
Work completed
Sanction on : 1 year 7 months ago
25 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 3 weeks ago
28 Dec 2023
Actual Completion Date : 7 months 3 weeks ago
30 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष । -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: