Work Profile Report [51W1173]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 15556 Dt. 31.3.2023
TS Amount (lakhs) : 332.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
332.79
Resanction Cost :
332.79
Tentative Cost :
332.79
Exp. Upto Last Fy :
129.41
For CFY 2024-2025
Remaining :
203.38
Demand :
203.38
Allotment :
155.34
Exp in CFY :
155.34
Total Up to Date Exp :
284.75
Construction Started
Sanction on : 1 year 8 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
75 %
Tentative Completion date on : 3 weeks 4 days ago
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 08-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: