Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.06 | 1.06 | 1.060 | 0 | 0.000 | 0.000 |
51W1190 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 47588 Dt. 28.6.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.63
Resanction Cost :
42.63
Tentative Cost :
42.63
Exp. Upto Last Fy : 9.70
For CFY 2024-2025
Remaining : 32.93
Demand : 32.93
Allotment : 13.00
Exp in CFY : 32.94
Total Up to Date Exp : 42.64
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
28 Jun 2023
Tentative Completion date:
3 months 2 weeks ago
30 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 04-Apr-2024
Physical Peramenters