Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.85 | 2.85 | 0.000 | 2.85 | 2.850 | 2.850 |
51W1191 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Letter No 895/07/ Yata PMGSY/ III Dt. 16.05.2023
TS Amount (lakhs) : 77.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
77.30
Resanction Cost :
77.30
Tentative Cost :
77.30
Exp. Upto Last Fy : 52.37
For CFY 2024-2025
Remaining : 24.93
Demand : 24.93
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 52.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
27 May 2024
Actual Completion Date:
1 month 2 weeks ago
27 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 10-Jun-2024
Physical Peramenters