Work Profile Report [51W1213]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E Letter No 60170 Dt. 06.10.2023
TS Amount (lakhs) : 152.01 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
152.01
Resanction Cost :
152.01
Tentative Cost :
152.01
Exp. Upto Last Fy :
131.09
For CFY 2024-2025
Remaining :
20.92
Demand :
20.92
Allotment :
1.26
Exp in CFY :
1.26
Total Up to Date Exp :
132.35
Work completed
Sanction on : 1 year 2 months ago
06 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 week ago
15 Dec 2023
Actual Completion Date : 1 year 1 week ago
15 Dec 2023
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: