Work Profile Report [51W1217]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 37290 Dt. 12 October 2023
TS Amount (lakhs) : 79.54 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
279.54
Resanction Cost :
279.54
Tentative Cost :
279.54
Exp. Upto Last Fy :
278.50
For CFY 2025-2026
Remaining :
1.04
Demand :
0.30
Allotment :
0.30
Exp in CFY :
0.30
Total Up to Date Exp :
278.80
In Maintenance After Completion
Sanction on : 2 years 3 months ago
12 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 week ago
15 Jan 2025
Actual Completion Date : 10 months 3 days ago
20 Mar 2025
Physical Linear Components
Remark
Overall Saving 0.74 has been recorded as expected cost of work reduced from 279.54 to 278.80 . -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: