Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.75 | 0.75 | 0.75 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 22 | 22 | 22 | 0 |
51W1218 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 34340 Dt. 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7.73
Resanction Cost :
7.73
Tentative Cost :
7.73
Exp. Upto Last Fy : 0.36
For CFY 2024-2025
Remaining : 7.37
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.36
Survey work done
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण। संमेरखण प्रस्ताव गठन का कार्य प्रगति में है। -- as on 04-Jan-2024
Physical Peramenters