Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.200 | 0 | 0.000 | 0.000 |
51W1240 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no 62222
TS Amount (lakhs) : 76.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.68
Resanction Cost :
76.68
Tentative Cost :
76.68
Exp. Upto Last Fy : 74.65
For CFY 2024-2025
Remaining : 2.03
Demand : 2.03
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 74.65
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 months 2 weeks ago
03 Nov 2023
Tentative Completion date:
6 months 2 weeks ago
30 Dec 2023
Actual Completion Date:
6 months 2 weeks ago
30 Dec 2023
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Physical Peramenters