Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
51W1250 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नगर निगम का पत्र संख्या 431/NCAP/paving of Road /2023-24 Dt. 7.8.2023
TS Amount (lakhs) : 50.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.32
Resanction Cost :
50.32
Tentative Cost :
50.32
Exp. Upto Last Fy : 32.71
For CFY 2024-2025
Remaining : 17.61
Demand : 17.61
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 32.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 06-May-2024
Physical Peramenters