Work Profile Report [51W1256]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : नगर निगम का पत्र संख्या 463/NCAP/Paving of Road /2023-24 Dt. 10.08.2023
TS Amount (lakhs) : 95.84 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
95.84
Resanction Cost :
95.84
Tentative Cost :
95.84
Exp. Upto Last Fy :
34.70
For CFY 2024-2025
Remaining :
61.14
Demand :
61.14
Allotment :
0.00
Exp in CFY :
42.46
Total Up to Date Exp :
77.16
Work completed
Sanction on : 1 year 3 months ago
10 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 5 months 3 weeks ago
31 May 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 28-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand