Work Profile Report [51W1260]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 56976 Dt.13.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.33
Resanction Cost :
30.33
Tentative Cost :
30.33
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
30.23
Demand :
30.23
Allotment :
0.90
Exp in CFY :
24.69
Total Up to Date Exp :
24.79
Construction Started
Sanction on : 11 months 2 weeks ago
13 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
42 %
Tentative Completion date on : 1 month 1 week ago
17 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 04-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: