Work Profile Report [51W1263]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E Letter no 40094 Dt. 24.01.2024
TS Amount (lakhs) : 6.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.55
Resanction Cost :
6.55
Tentative Cost :
6.55
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
6.45
Demand :
5.29
Allotment :
4.59
Exp in CFY :
2.29
Total Up to Date Exp :
2.39
Unstarted Work
Sanction on : 11 months 1 day ago
24 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण हेतु DPR गठन का कार्य प्रगति पर है। -- as on 29-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: