Work Profile Report [51W1324]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E Letter no. 37290
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.91
Resanction Cost :
243.91
Tentative Cost :
243.91
Exp. Upto Last Fy :
20.10
For CFY 2025-2026
Remaining :
223.81
Demand :
223.81
Allotment :
85.15
Exp in CFY :
85.15
Total Up to Date Exp :
105.25
Construction Started
Sanction on : 3 months 4 weeks ago
28 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
65 %
Tentative Completion date on : 1 week 6 days from now
11 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 30-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: