Work Profile Report [51W1341]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No.34340 PWD Anubhag-2 Dehradun Dt. 14.10.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
319.30
Resanction Cost :
319.30
Tentative Cost :
319.30
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
319.30
Demand :
75.00
Allotment :
35.22
Exp in CFY :
35.22
Total Up to Date Exp :
35.22
Construction Started
Sanction on : 3 months 1 week ago
14 Oct 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
20 %
Tentative Completion date on : 7 months 3 weeks from now
19 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 15-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: