Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
52W261 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2477/।।।(2)/16-01(मु0मं0घो0) /2016 दिनांक 20 सितम्बर 2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.60
Resanction Cost :
26.60
Tentative Cost :
26.60
Exp. Upto Last Fy : 1.40
For CFY 2024-2025
Remaining : 25.20
Demand : 25.20
Allotment : 7.56
Exp in CFY : 0.00
Total Up to Date Exp : 1.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 25 %
Sanction on :
7 years 9 months ago
20 Sep 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
शा0सं0-ई-पत्रावली संख्या-35334 लोक निर्माण अनुभाग-2, देहरादून दिनांक 11.03.2024 द्वारा लम्बाई 3.475 में रू0 104.38लाख की स्वीकृति प्राप्त एवं निविदा आमंत्रित की जा चुकी है। -- as on 15-Mar-2024
Physical Peramenters